Applies to: [Form Manager]

Problem: How do I change the time frame that my statistical graph is referencing?

Solution: On the right side of the graph are four options: Today, Week, Month, and Year. Clicking on of those words will update the graph. You will know the graph has been updated because it will reload, and then the orange banner at the top of the graph will reflect the new time period. For example, if the month is January and you click on "Month," the banner will change to say "January 200X."